4 Analysis outsourcing of the procurement
4.2.2.2 Process costs of the paged out procurement without participation of the purchase department
Starting from 2002 those could arrange customer GmbH their procurement process in such a manner that the purchase department no more did not have to concern itself with the procurement of B and C-parts.
Here this situation is analyzed, which can be called actual outsourcing of the procurement. In the phase of the materialanforderung the first activities remain unchanged.
Only after the permission of the material requirement light one differentiates whether the inquired product represents an A-article or a B and/or an C-article. In the first case the outsourcing is not meaningful, because specific investments are necessary (see chapters. 4.1). Therefore the procurement process of the A-parts does not change.
In the following table the activity times are alike, but sink the frequency of sending authorized the material requirement light away and the telephone reminder of the purchase department on in each case 6,6 and 0,4-mal on the day, since they concern only the A-parts.
Accordingly also their proportional load sinks.
Personnel expenditure |
Proportional load |
Activity costs |
Activities |
Production department: 1.000.000 € |
0,57% |
5.700,- € |
Materials requirements examine |
0,46% |
4.600,- € |
Material requirement lights provide |
|
0,23% |
2.300,- € |
Material requirement lights to the range leader send |
|
0,23% |
2.300,- € |
Signature/permission of the range leader |
|
0,21% |
2.100,- € |
Authorized material requirement lights to the purchase department send |
|
0,01% |
100,- € |
Telephone reminders of the purchase department |
|
0,19% |
1.900,- € |
Outsourcing order |
|
1,90% |
19.000,- € |
Sum for the activity: Materialanforderung |
|
Purchase department: 250.000 € |
0,18% |
450,- € |
Material requirement lights receive |
1,38% |
3.450,- € |
Orders and/or orders provide |
|
0,57% |
1.425,- € |
Confirmation of orders inquire and receive |
|
0,34% |
850,- € |
Order copies distribute |
|
0,46% |
1.150,- € |
Orders placings |
|
0,06% |
150,- € |
Reminders of the supplier |
|
2,99% |
7.475,- € |
Sum for the activity: Order and/or order (only A-parts) |
|
Camp: 200.000 € |
5,00% |
10.000,- € |
Commodity acceptance |
2,71% |
5.420,- € |
Merchandise controls |
|
0,26% |
520,- € |
Clarifying with suppliers and/or Requesters |
|
7,97% |
15.940,- € |
Sum for the activity: Incoming goods |
|
Bookkeeping: 150.000 € |
1,55% |
2.325,- € |
Calculations receive |
0,56% |
840,- € |
Calculations to approve leave |
|
0,42% |
630,- € |
Clarifying over calculation discrepancies |
|
2,53% |
3.795,- € |
Sum for the activity: Audit |
|
Administration: 200.000 € |
4,02% |
8.040,- € |
Calculations pay |
0,77% |
1.540,- € |
Calculations placings |
|
1,04% |
2.080,- € |
Clarifying with the bank |
|
5,83% |
11.660,- € |
Sum for the activity: Zahlungsabwicklung |
Structure and machinery costs |
Proportional load |
Activity costs |
Activities |
Production department: 1.400.000 € |
0,57% |
7.980,- € |
Materials requirements examine |
0,46% |
6.440,- € |
Material requirement lights provide |
|
0,23% |
3.220,- € |
Material requirement lights to the range leader send |
|
0,23% |
3.220,- € |
Signature/permission of the range leader |
|
0,21% |
2.940,- € |
Authorized material requirement lights to the purchase department send |
|
0,01% |
140,- € |
Telephone reminders of the purchase department |
|
0,19% |
2.660,- € |
Outsourcing order |
|
1,90% |
26.600,- € |
Sum for the activity: Materialanforderung |
|
Purchase department: 25.000 € |
0,18% |
45,- € |
Material requirement lights receive |
1,38% |
345,- € |
Orders and/or orders provide |
|
0,57% |
142,50 € |
Confirmation of orders inquire and receive |
|
0,34% |
85,- € |
Order copies distribute |
|
0,46% |
115,- € |
Orders placings |
|
0,06% |
15,- € |
Reminders of the supplier |
|
2,99% |
747,50 € |
Sum for the activity: Order and/or order (only A-parts) |
|
Camp: 100.000 € |
5,00% |
5.000,- € |
Commodity acceptance |
2,71% |
2.710,- € |
Merchandise controls |
|
0,26% |
260,- € |
Clarifying with suppliers and/or Requesters |
|
7,97% |
7.970,- € |
Sum for the activity: Incoming goods |
|
Bookkeeping: 25.000 € |
1,55% |
387,50 € |
Calculations receive |
0,56% |
140,- € |
Calculations to approve leave |
|
0,42% |
105,- € |
Clarifying over calculation discrepancies |
|
2,53% |
632,50 € |
Sum for the activity: Audit |
|
Administration: 25.000 € |
4,02% |
1.005,- € |
Calculations pay |
0,77% |
192,50 € |
Calculations placings |
|
1,04% |
260,- € |
Clarifying with the bank |
|
5,83% |
1.457,50 |
Sum for the activity: Zahlungsabwicklung |
Energy and materials consumption |
Proportional load |
Activity costs |
Activities |
Production department: 250.000 € |
0,57% |
1.425,- € |
Materials requirements examine |
0,46% |
1.150,- € |
Material requirement lights provide |
|
0,23% |
575,- € |
Material requirement lights to the range leader send |
|
0,23% |
575,- € |
Signature/permission of the range leader |
|
0,21% |
525,- € |
Authorized material requirement lights to the purchase department send |
|
0,01% |
25,- € |
Telephone reminders of the purchase department |
|
0,19% |
475,- € |
Outsourcing order |
|
1,90% |
4.750,- € |
Sum for the activity: Materialanforderung |
|
Purchase department: 5.000 € |
0,18% |
9,- € |
Material requirement lights receive |
1,38% |
69,- € |
Orders and/or orders provide |
|
0,57% |
28,50 € |
Confirmation of orders inquire and receive |
|
0,34% |
17,- € |
Order copies distribute |
|
0,46% |
23,- € |
Orders placings |
|
0,06% |
3,- € |
Reminders of the supplier |
|
2,99% |
149,50 € |
Sum for the activity: Order and/or order (only A-parts) |
|
Camp: 15.000 € |
5,00% |
750,- € |
Commodity acceptance |
2,71% |
406,50 € |
Merchandise controls |
|
0,26% |
39,- € |
Clarifying with suppliers and/or Requesters |
|
7,97% |
1.195,50 € |
Sum for the activity: Incoming goods |
|
Bookkeeping: 25.000 € |
1,55% |
387,50 € |
Calculations receive |
0,56% |
140,- € |
Calculations to approve leave |
|
0,42% |
105,- € |
Clarifying over calculation discrepancies |
|
2,53% |
632,50 € |
Sum for the activity: Audit |
|
Administration: 25.000 € |
4,02% |
1.005,- € |
Calculations pay |
0,77% |
192,50 € |
Calculations placings |
|
1,04% |
260,- € |
Clarifying with the bank |
|
5,83% |
1.457,50 € |
Sum for the activity: Zahlungsabwicklung |